The expansion, designed with
community, staff and patient input,
was delivered on time and on budget
in just 25 months and took place with-
out disrupting essential and lifesaving
clinical services at the existing hospital
building. The project, which employed
600 workers at its construction peak
and created 200 new jobs within the
hospital, transferred significant risk
to the private sector partner and
resulted in projected cost savings of
$124.9 million.
“This project is remarkable in how well
the community, health-care staff and
partners worked together to create an
integrated hospital that truly put the
needs of Milton residents at its core,”
said the awards committee.