ultimately upgrade passenger flow,
transfer experience, and relation to
the neighbourhood. Graham’s scope
of work included three new Station
Houses, improved access via escala-
tors, elevators, staircases and four
new points of access to the platform,
extended roofs, three station vesti-
bules and ancillary buildings, bike
storage, as well as upgrades to Central
Boulevard and a new plaza area.
Graham mobilized on March 5th, 2015.
Careful planning and substantial rein-
forcing to the existing Station struc-
ture were done prior to an extremely
complex demolition process, which
allowed the trains and full public
access with no interruptions through-
out the Project while the structure of
the existing platform was modified
to accommodate new stairs, eleva-
tors and eight new escalators. During
Photo Credit - Ed White
JANUARY 2019 | BUSINESS ELITE CANADA 167