Page 5 - Chinook Power Station
P. 5

“It took over 2 million on-site labour hours to safely

        build the Chinook Power Station. We worked                   “One of our strategic priorities

        extensively at the beginning of the project to make          is to modernize the grid, while
        sure our design would not require costly revisions           reducing our greenhouse gas

        later on down the line and we also met regularly           emissions in accordance with our
        throughout the project to review project risks                          2030 targets.”

        and adjust our forecast, so we were able to bring

        the project in under budget. That was definitely a
        positive thing for SaskPower,” says Cherry.             equipment of this size and therefore this work

                                                                required the company to source equipment from
        ECONOMIC SPIN-OFFS                                      outside Saskatchewan and Canada.




        In total, $430 million worth of contracts were          “Wherever possible, we used local services to
        available on Chinook. Cherry says it’s important        complete aspects related to this work that could be

        to note that for the largest contracts available (e.g.   done locally (e.g. installing the equipment built out-

        turbines and generators) no local companies had         of-country and general construction activities with
        the experience or capability to build and install       local resources),” says Cherry.