• Natural light                                         spring 2022. It will be carried out in two phases. The
        • Universal accessibility                               first phase will last from spring 2019 to spring 2020

        • Building envelope with superior energy efficiency     and will involve preparatory work, including building

        • Energy efficient mechanical and heat recovery         demolition, removal of materials and waste, soil
        system                                                  decontamination and excavation of the rock bed.

        • Water catchment and recycling                         The second phase will last from spring 2020 to
        • Green space to reduce urban heat islands              spring 2022 and will involve construction of the new

        • Use of CLT wood on the roofs of the offices           bus garage.

        • Recovery of construction materials, when possible
                                                                BEC: What is the economic impact of this project?

        BEC:  Please describe the project phases.               GL: The project has an overall construction schedule

        GL: The work will take place from spring 2019 to        of 34 months. An average of 200 employees will