• Natural light spring 2022. It will be carried out in two phases. The
• Universal accessibility first phase will last from spring 2019 to spring 2020
• Building envelope with superior energy efficiency and will involve preparatory work, including building
• Energy efficient mechanical and heat recovery demolition, removal of materials and waste, soil
system decontamination and excavation of the rock bed.
• Water catchment and recycling The second phase will last from spring 2020 to
• Green space to reduce urban heat islands spring 2022 and will involve construction of the new
• Use of CLT wood on the roofs of the offices bus garage.
• Recovery of construction materials, when possible
BEC: What is the economic impact of this project?
BEC: Please describe the project phases. GL: The project has an overall construction schedule
GL: The work will take place from spring 2019 to of 34 months. An average of 200 employees will