In addition to enhancing accessibility, the new interchange adheres to modern structural and seismic design standards. “We’ve ensured a clearance of five metres under the new overpass— half a metre more than the original—aligning with current safety standards,” he adds. Construction on the Steveston Interchange began in 2022 and is being executed in two phases to minimize disruptions to the travelling public. In Phase 1, crews constructed a two-lane structure on the north side of the existing overpass, which was opened to traffic in January 2025. With traffic now Excavators working to remove the original Steveston Interchange (February 2025) 64 JUN 2025 | BUSINESS ELITE CANADA