“We are now entering the transition phase between the completion of construction and the preparation for the activation of hospital services,” says Ouellet. Pavilion A, a four-storey building, is more than 89 percent complete overall. Structural work and the exterior envelope have been completed, while architectural work has reached 83 percent completion and mechanical and electrical systems are 95 percent complete. Pavilion B, the larger 13-storey building, has surpassed 80 percent completion. The structure is complete, while the exterior envelope is 92 percent complete and expected to be finished by the end of 2026. Interior architectural work has reached 81 percent completion, with mechanical and electrical systems at 86 percent. Finishing work has begun 5